SCADA supervision for the milk pasteurisation plant

A dairy company commissioned Treesse Progetti to replace its existing HMI system with a more comprehensive and functional supervision platform, equipped with four monitors and designed to improve the user experience and facilitate the operators' daily tasks.  

Client: Dairy company

Sector: Dairy

Intervention: New SCADA system

Technologies: Ignition Perspective, Siemens S7-1500 and S7-300 PLCs, Ignition Gateway on a virtual machine

Objective: Development of a SCADA system for plant supervision and control

17
Synoptic panels developed for the entire plant
0
Modifications to existing PLC software
The challenge
Clearer and more readable on-board control panel

The challenge was to make the plant more functional and "readable" for operators by replacing the existing HMI with a more modern SCADA system.

The solution
Ignition SCADA

Ignition Perspective SCADA system replacing the existing HMI for plant monitoring and management. The Gateway runs on a VM at the client's site. Two workstations: one in production with four monitors for control and production cycles, and one in the offices for remote consultation. The system, based on the client's Ignition licences, communicates with the existing Siemens S7-1500 and S7-300 PLCs.

The constraint
Integration with existing automation

The main technical challenge was developing the new SCADA system by adapting it to the structure and logic of the existing PLC software without modifying its operation. The integration required careful attention to variable management and interaction with the already implemented automation logic, ensuring the plant's operational continuity.

How we worked
Development, testing, commissioning

After defining objectives and requirements with the client, we developed the solution at our premises. The work includes interactive synoptics, interfaces for production and cleaning cycles, windows for configuring process parameters and pasteurisation cycles, monitoring, PID tuning, alarm management, historical trends, and auditing.

The result

Archived data and alarms

Process variables and alarms are recorded and logged to support analysis and traceability.

Integration with existing PLC software

The SCADA was integrated with the existing automation system, keeping the control logic and PLC software unchanged.

Existing licences utilised

The project leveraged the Ignition Perspective licences already owned by the client, keeping the investment down.

Scalable control

The developed system allows for the expansion of control to portable devices (such as tablets) so that operators can manage specific functions directly in the field.

image of manufacturing plant interior
image of maintenance crew working on aircraft

Frequently asked questions

What we did in this project and what to consider before switching from an operator panel to a SCADA system.

Can the existing operator panel remain active?

It depends on the PLC software structure; potentially, the existing operator panel can remain active and work in parallel with the new SCADA.

Are new servers required for the SCADA?

No: Ignition was installed on a virtual machine within the client's existing infrastructure; a PC and monitors were provided.

Do you have a system that needs work?

Tell us about your requirements: one of our engineers will get back to you to assess feasibility and timelines together.