FIM CAST commissioned Treesse Progetti to upgrade the moulding department's control system: new PLC, integrated safety and WinCC supervision, all completed during a single scheduled shutdown in August.
Client: FIM CAST
Sector: Foundry
Project: Complete automation retrofit
Technologies: Siemens 1517F-3 PN/DP, WinCC 8.1, Profinet®/Profisafe®
Objective: Overcome obsolescence while keeping safety unchanged
While the mechanics of the sand-resin plant had stood the test of time, the automation was showing its age; downtime causes were difficult to identify, updates and patches had been added over the years, manual restarts were required after every shutdown, and hardware (S7-300, PILZ safety, optical Profibus) was becoming increasingly difficult to source.
All automation software was centralised into a Siemens 1517F-3 PN/DP CPU, installed in a clean zone outside the production area. Remote ET200 nodes replaced the S7-300, functional safety was integrated into the PLC, and the carriages communicate via radio using Profinet® and Profisafe®.
Functions, performance, and safety logic had to remain unchanged to classify the work as extraordinary maintenance. Dismantling, installation, wiring, and testing had to be completed between 1st and 31st August.
The PLC and HMI were rewritten from scratch, with simplified cycles, revamped alarms, and a new commissioning function for use after unexpected shutdowns. WinCC was upgraded from 7.5 to 8.1 on Hyper-V, with one server and three clients.
Alarm management overhauled and logic simplified, so downtime causes can be identified directly from the supervisor.
After an unexpected shutdown, the phasing procedure returns the cycle to known conditions without manual intervention or supervision.
S7-300 and dedicated safety replaced by a single platform, with available spare parts.
Functions replicated identically, no changes to the risk assessment.
.jpeg)
.jpeg)
.jpeg)
What we did in this project and what to evaluate before replacing a PLC.
In the FIM CAST case, the work was completed during a single four-week scheduled shutdown in August.
No: the safety logic has been replicated identically and the replaced devices have an equivalent or higher PL, so the existing analyses remain valid.
It eliminates dedicated hardware and reduces electromechanics, with fewer critical components to manage and maintain.
Tell us about your requirements: one of our engineers will get back to you to assess feasibility and timelines together.